Ah ha
-
1. Defence Information Infrastructure
The Ministry of Defence’s secure military network was built to help British troops operate more effectively around the world. The MoD gave parliament a figure of £2.3 billion, but a report by MPs has shown that they knew that the project would cost at least £5.8 billion. The true figure has since risen to at least £7.1 billion. By 2008, the programme was running at least 18 months late, had provided only 29,000 of a contracted 63,000 terminals, and had supplied none of the contracted Secret capability.
According to the then chairman of the PAC, Edward Leigh, there was no suitable pilot carried out for such a multifaceted programme. The condition of the Department’s buildings where the system was to be installed was badly miscalculated due to insufficient research.
These disasters could all have been adverted by better planning and listening to expert advice. If your business needs project management advice, fill in the form on the right and the experts at Software Advisory Service can provide impartial, non-chargeable advice to help you avoid the next major catastrophe.
-
2. NHS National Program for IT
In September 2013, an NHS patient record system that would have been the world’s largest non-military IT system was abandoned, in what could be the most catastrophic IT failure ever seen by the government. The failed centralised e-record system cost the taxpayer over £10 billion, £3.6 billion more than ministers had anticipated.
From the outset, the project was plagued by delays. The delivery of core systems was stalled due to fears that some software was not fit for purpose. After seven years, only 13 acute trusts out of 169 received the full patient administration systems they were agreed under the National Programme. The new systems also caused chaos for many users; a newly-installed IT system lost Barts NHS Trust thousands of patient records, delaying the treatment of urgent cases, costing millions in additional staff and warranting an internal investigation. The Milton Keynes Foundation Trust wrote a cautionary letter to the times about the inefficacy of their system, and warning others not to use it.
-
3. Scottish Parliament Building
The Scottish Parliament Building has been controversial for a host of things, including its location, architect and design – it’s described by one particularly glorious TripAdvisor review as a “grotesque brutalist mess” – but the reason a public enquiry was made into its construction was because of constant delays and its escalating cost. Initially scheduled to inaugurate in 2001, its doors finally opened three years later with an estimated cost of £414million, much higher than its original estimate of £10-40 million. The inquiry found incompetence in the management of the entire project, including fulfilment of cost and the way major design changes were added.
The cost hasn’t stopped there. Figures have revealed that the building’s average repair bill has reached £141,000 per month, five times the figure during the building’s first year. This means that since 2004, maintenance costs have set taxpayers back by £11 million, which of course is higher than some of the initial estimates for the cost of constructing the building itself.
Yeah there’s plenty more,
So how to pay for it?
Stop having big ideas and big projects and fucking them up!
(HS2 & 3, Crossrail 2)
Sorted and you can still give the 350mil to the NHS